Data Center Market Update: Week of August 31, 2026
Anthropic books $35B with Nvidia-backed Lambda and Crusoe signs $13B with Jane Street, Flex buys EPC Power for $4.4B, Bangkok lands a hyperscaler, and California sends ratepayer bills to Newsom.

This week’s news confirms that the AI compute market, not colocation supply, is where the biggest dollar figures are moving: Anthropic booked roughly $35 billion of Lambda capacity and Crusoe signed a $13 billion contract with trading firm Jane Street, two deals that together exceed the market value of many public data center REITs. Power electronics saw its own consolidation move with Flex’s $4.4 billion purchase of EPC Power, Bangkok landed a hyperscaler pre-lease, California pushed ratepayer-protection bills to the governor’s desk, and Equinix closed its $4.1 billion Nordic acquisition.
Key takeaways
- Anthropic agreed to a roughly $35 billion multi-year deal with Nvidia-backed Lambda, reported 31 August-1 September 2026, with Nvidia holding the lease on Hut 8’s ~350MW Beacon Point campus in Texas — the fourth mega-deal Anthropic has signed in 2026 after Nscale ($45B), Fluidstack ($50B) and SpaceX ($45B).
- Crusoe signed a five-year, ~$13 billion AI cloud contract with Jane Street Group (reported 3 September), helping it close a $3 billion funding round at a $30 billion valuation.
- Flex will acquire power-conversion maker EPC Power for $4.4 billion (announced 3 September), betting on 800V DC architecture as AI rack densities push past what conventional AC distribution can handle efficiently.
- Evolution Data Centres pre-leased the first 12MW phase of its Bangkok TH01 campus to an unnamed tier-1 hyperscaler, with a second 40MW AI-focused phase due Q2 2027 — the latest sign Thailand is converting BOI-approved pipeline into signed tenants.
- California’s SB 886 and AB 2383 passed the legislature and are on Governor Newsom’s desk; if signed, they require the CPUC to set separate large-load tariffs so grid-upgrade costs aren’t spread across residential ratepayers, with final tariffs due by 1 July 2027.
- Equinix and CPP Investments completed their $4.1 billion acquisition of Nordic operator atNorth on 2 September, eight months after the deal was announced.
- H100 rental pricing held flat at $1.49-6.98/GPU-hour; B200 pricing spread widened to $5.91-16.11/GPU-hour as hyperscaler on-demand rates diverge further from specialist-cloud marketplaces.
Anthropic’s $35 billion Lambda deal: the lease structure is the story
Bloomberg and the Wall Street Journal reported on 31 August-1 September 2026 that Anthropic agreed to a roughly $35 billion, multi-year compute deal with Nvidia-backed cloud provider Lambda. The structural detail that matters for anyone tracking data center financing: Nvidia itself will hold the lease on the underlying facility — Hut 8’s roughly 350MW Beacon Point campus in Nueces County, Texas — while Lambda operates the site and supplies Anthropic with Nvidia chips. That arrangement lets Nvidia underwrite build-out risk on a facility it doesn’t operate, a financing pattern also visible in some of the vendor-backed deals covered in our AI data center financing guide. The Lambda deal is Anthropic’s fourth mega-commitment of 2026, following $45 billion with Nscale, $50 billion with Fluidstack, and $45 billion with SpaceX — a run rate that puts Anthropic’s disclosed 2026 compute commitments well past $150 billion.
Crusoe-Jane Street: a trading firm becomes a marquee AI cloud customer
Crusoe, which started in 2018 as a flared-gas crypto miner before pivoting to hyperscale AI infrastructure for clients including Oracle and OpenAI, signed a five-year cloud contract worth roughly $13 billion with Jane Street Group, Bloomberg reported on 3 September 2026. The contract supplies GPU clusters for AI training and inference and is Crusoe’s highest-profile customer win yet. The deal’s visibility helped Crusoe close a new $3 billion funding round at a $30 billion valuation days later, co-led by Atreides Management and Valor Equity Partners. For colocation buyers, the signal is that demand for dedicated GPU capacity is no longer confined to AI labs and hyperscalers — quantitative trading firms are now signing contracts at a scale that rivals mid-tier cloud providers’ entire balance sheets.
Flex buys EPC Power for $4.4 billion, betting on 800V DC
Flex Ltd. announced on 3 September 2026 that it will acquire EPC Power, a California-based maker of 800V DC power-conversion and grid-forming systems, for $4.4 billion in cash and debt. EPC Power has deployed more than 15GW of equipment across 62 countries since 2010 and is projected to generate roughly $800 million in 2026 revenue with about 40% organic growth forecast for 2027. The deal is expected to close in Q4 2026, after which EPC Power joins Flex’s Cloud and Power Infrastructure segment — itself slated for a standalone public listing in Q1 2027. Higher-voltage DC distribution moves more power at lower current, cutting conductor size and losses as AI rack densities climb well past the 50-100kW range; see our generator and backup power guide for how power architecture choices ripple through site design.
Bangkok lands a hyperscaler pre-lease
Evolution Data Centres, working with Thai developer Central Pattana, signed a pre-lease for the first 12MW phase of its TH01 campus in Bang Na, Bangkok, with an unnamed tier-1 global hyperscaler, DatacenterDynamics reported on 4 September 2026. The phase is due online in Q4 2026; a second, AI-focused 40MW phase follows in Q2 2027. The project’s projected PUE is below 1.3. It’s the latest tenant win to convert Thailand’s approved investment pipeline — see our Thailand data center boom guide for the THB 746 billion BOI approval total — into signed capacity, reinforcing Bangkok’s position alongside Johor and Singapore as Southeast Asia’s third major hub.
California sends ratepayer-protection bills to Newsom
SB 886 (Sen. Steve Padilla) and AB 2383 (Assemblymember Rick Chavez Zbur) cleared the California legislature in early September 2026 and now sit on Governor Newsom’s desk, with a decision due by the end of the month. The compromise framework requires the California Public Utilities Commission to establish separate electricity tariffs and updated interconnection rules specifically for large data center loads, so the cost of grid upgrades triggered by data centers isn’t spread across residential ratepayers. The CPUC has until 1 July 2027 to finalize the tariffs. California joins a growing list of states — see our interconnection guide for how utilities elsewhere are handling large-load queues — moving to formalize cost allocation rather than negotiate it case by case.
Equinix closes $4.1 billion atNorth acquisition
Equinix and Canada Pension Plan Investment Board completed their acquisition of Nordic operator atNorth on 2 September 2026, roughly eight months after the deal was first announced in February. CPP Investments holds about 51% of the resulting venture after committing $1.3 billion, Equinix holds about 34% ($895 million), and Partners Group holds about 10% ($260 million); atNorth’s own stakeholders rolled over a substantial portion of their equity. atNorth operates seven data centers across Sweden, Iceland and Finland, with further sites under development in Finland, Denmark, Norway and Sweden — Equinix said the deal is immediately accretive to its adjusted funds from operations per share. It’s a reminder that consolidation isn’t confined to AI-native operators; see our hyperscale vs. colocation guide for how pension-fund capital is increasingly the buyer of record in these deals.
GPU pricing: H100 flat, B200 spread widens
H100 rental rates held steady week over week at $1.49-1.99/GPU-hour on marketplaces (Vast.ai, RunPod) up to $6.98/GPU-hour on hyperscalers. B200 pricing showed a wider spread than in prior weeks: Vast.ai’s marketplace median sits near $5.91/GPU-hour while AWS’s on-demand p6-b200 instance runs $14.24/GPU-hour, with some hyperscaler quotes reaching $16.11. The gap reflects continued allocation constraints on Blackwell-generation hardware — enterprise customers routing through specialist clouds are getting materially better rates than those relying on hyperscaler on-demand capacity. Compare current listings on our GPU price tracker.
Table: this week’s largest disclosed transactions
| Deal | Parties | Value | Date reported |
|---|---|---|---|
| AI cloud capacity | Anthropic - Lambda (Nvidia-backed) | ~$35B | 31 Aug-1 Sep 2026 |
| AI cloud capacity | Crusoe - Jane Street | ~$13B | 3 Sep 2026 |
| M&A, power electronics | Flex - EPC Power | $4.4B | 3 Sep 2026 |
| M&A, colocation (closed) | Equinix/CPP - atNorth | $4.1B | 2 Sep 2026 (closed) |
| Funding round | Crusoe (Atreides, Valor Equity Partners) | $3B at $30B valuation | 3 Sep 2026 |
Table: GPU rental pricing, week of September 7, 2026
| GPU | Low (marketplace) | High (hyperscaler) | Trend vs. prior week |
|---|---|---|---|
| H100 | $1.49/hr (Vast.ai) | $6.98/hr | Flat |
| B200 | $5.91/hr (Vast.ai) | $14.24-16.11/hr (AWS and other hyperscalers) | Spread widened |
What this means for buyers
Two patterns stand out for anyone budgeting AI capacity or colocation space this quarter. First, the largest compute deals ($35B Lambda, $13B Jane Street) are increasingly structured with the chip vendor or a third party holding the underlying real-estate lease rather than the buyer — worth checking who actually holds facility risk before treating a “deal size” headline as capacity you can rely on. Second, cost allocation is becoming an explicit regulatory variable, not just a site-selection one: California’s pending tariff framework and the broader FERC large-load docket mean the effective price of power at a given site will increasingly depend on which state or ISO territory it sits in, not just the posted utility rate. Buyers evaluating new sites should treat pending state-level tariff reform as a due-diligence item alongside interconnection queue position — see current facility data on our data center index and country-level listings at /data-centers/, or request pricing through our quote form.
Sources
This update draws on reporting from Bloomberg, TechCrunch, Data Center Knowledge, DatacenterDynamics, Hoodline, Equinix’s newsroom, IntuitionLabs and Thunder Compute, linked above. Facility-level figures are cross-checked against our own colocation price index methodology where applicable.
Частые вопросы
How big is Anthropic's new cloud deal with Lambda?
Anthropic agreed to a roughly $35 billion, multi-year compute deal with Nvidia-backed cloud provider Lambda, reported by Bloomberg and the Wall Street Journal on 31 August-1 September 2026. Nvidia will hold the lease on the data center itself — Hut 8's roughly 350MW Beacon Point campus in Nueces County, Texas — while Lambda operates it with Nvidia chips. It follows Anthropic's $45B Nscale deal, $50B Fluidstack deal and $45B SpaceX deal signed earlier in 2026.
What is the Crusoe-Jane Street deal worth?
Crusoe signed a five-year, roughly $13 billion AI cloud contract with trading firm Jane Street Group, first reported by Bloomberg on 3 September 2026. It is Crusoe's highest-profile customer to date and helped the company close a new $3 billion funding round at a $30 billion valuation, up from a crypto-mining startup founded in 2018.
Why did Flex pay $4.4 billion for EPC Power?
Flex Ltd. announced on 3 September 2026 that it will acquire EPC Power, a maker of 800V DC power-conversion and grid-forming equipment for AI data centers, for $4.4 billion. EPC Power has shipped more than 15GW of equipment across 62 countries and is projected to generate about $800 million in 2026 revenue; the unit joins Flex's Cloud and Power Infrastructure segment ahead of a planned 2027 spinoff.
What happened with Evolution DC's Bangkok data center?
Evolution Data Centres signed a pre-lease with an unnamed tier-1 global hyperscaler for the first 12MW phase of its TH01 campus in Bang Na, Bangkok, announced 4 September 2026. The phase is due online in Q4 2026; a second 40MW AI-focused phase is due in Q2 2027. The project is a joint venture with Thai developer Central Pattana.
What do California's new data center bills do?
SB 886 and AB 2383 passed the California legislature in early September 2026 and are on Governor Newsom's desk with a decision due by the end of the month. The bills direct the California Public Utilities Commission to set separate electricity tariffs and updated interconnection rules for large data centers, so grid-upgrade costs are not passed to residential ratepayers; the CPUC has until 1 July 2027 to finalize the tariffs.
Did the Equinix-atNorth acquisition close?
Yes. Equinix and Canada Pension Plan Investment Board (CPP Investments) completed their $4.1 billion acquisition of Nordic operator atNorth on 2 September 2026, about eight months after it was first announced in February. CPP Investments holds roughly 51% of the venture, Equinix about 34%, and Partners Group about 10%; atNorth runs seven data centers in Sweden, Iceland and Finland with more under development in Finland, Denmark, Norway and Sweden.
What are current GPU rental prices for H100 and B200?
H100 spans roughly $1.49-1.99/GPU-hour on marketplaces such as Vast.ai and RunPod up to $6.98 on hyperscalers, largely unchanged week over week. B200 pricing has widened to roughly $5.91-16.11/GPU-hour — Vast.ai's marketplace median near $5.91 against AWS's on-demand p6-b200 rate of $14.24, reflecting how allocation-gated hyperscaler capacity still commands a large premium over specialist clouds.
Источники
Первоисточники, на которые опирается статья. Каждая цифра ведёт туда, откуда она взята.
- Bloomberg: Crusoe Signs Roughly $13 Billion AI Cloud Deal With Jane Street
- Bloomberg: Anthropic Strikes $35 Billion Cloud Deal With Nvidia-Backed Lambda
- TechCrunch: Crusoe reportedly raises $3B at a $30B valuation
- Data Center Knowledge: Flex Pays $4.4B for EPC Power as AI Data Centers Push 800V Architecture
- DatacenterDynamics: Evolution DC signs pre-lease for first phase of Bangkok data center to unnamed hyperscaler
- DatacenterDynamics: California lawmakers pass data center ratepayer protection bills, send to governor for approval
- Hoodline: California Data Center Bills Head to Newsom's Desk
- Equinix newsroom: CPP Investments and Equinix Complete atNorth Acquisition
- IntuitionLabs: H100 Rental Prices Compared — $1.49-$6.98/hr Across 15+ Cloud Providers