1 The Coloprice catalogue lists 6,119 data centers from 2,295 operators in 184 countries.
coloprice.com/data-centers/ · as of
2 1,719 of 6,119 listed facilities publish IT power; together they total 118,664 MW.
coloprice.com/data-centers/ · as of
3 50.7 GW of data center capacity is under construction and 34.6 GW is announced across 590 tracked projects (published capacity only).
coloprice.com/pipeline/ · as of · CSV ↓
4 United States leads the construction pipeline with 33.4 GW under construction across 178 projects.
coloprice.com/pipeline/ · as of · CSV ↓
5 Wholesale colocation ranges from $160 per kW per month in São Paulo to $403 in Singapore across 23 index markets (H2 2025 – Q2 2026).
coloprice.com/index/ · as of · JSON ↓
6 The median wholesale colocation price across 23 index markets is $200 per kW per month (H2 2025 – Q2 2026).
coloprice.com/index/ · as of · JSON ↓
7 NVIDIA H100 on-demand rental runs $1.3–$12.29 per GPU-hour across tracked providers, median $3.9; 10 GPU models tracked.
coloprice.com/gpu/ · as of · JSON ↓
8 NVIDIA GB200 is the most expensive tracked GPU: median $13.25 per GPU-hour on demand, $10.58 on a one-year commitment.
coloprice.com/gpu/ · as of · JSON ↓
9 Chinese BESS tenders average $83/kWh for 4-hour and $104/kWh for 2-hour systems, against a $117/kWh global turnkey benchmark; 19 systems tracked.
coloprice.com/bess/ · as of · JSON ↓
10 Commercial electricity for data centers spans $0.014/kWh in Angola to $0.454/kWh in UK across 126 markets.
coloprice.com/energy/ · as of · CSV ↓
11 61 government and grid-operator restrictions on new data centers are on record in 16 countries; 45 are in force.
coloprice.com/restrictions/ · as of · CSV ↓
12 47 data center tax incentive programs are catalogued across 44 jurisdictions in 9 countries.
coloprice.com/incentives/ · as of · CSV ↓
13 141 data center incidents are documented from 2015 to 2026; the leading cause is power, 23% of cases.
coloprice.com/incidents/ · as of · CSV ↓
14 1,166 facilities hold a third-party tier certificate across 116 countries; India leads with 92.
coloprice.com/tiers/ · as of · CSV ↓
15 Greater Jakarta is the largest metro market by facilities tracked: 118 data centers, 3,510 MW published, 74 operators.
Market figures from primary sources
Market size & capex
16 Global data center capex has been raised to more than $1 trillion in 2026 and is now forecast to surpass $3 trillion annually by 2030 — nearly double Dell'Oro's January 2026 outlook of $1.7 trillion.
17 Cumulative data center investment need for 2025–2030 is estimated at $6.7 trillion, of which $5.2 trillion is for AI capacity.
18 The colocation market is worth $91–104B in 2025 and is projected to reach $165–204B by 2030 (14–16% CAGR).
19 About 100 GW of new data center capacity will be delivered worldwide in 2026–2030, creating roughly $1.2 trillion of real estate value.
Capacity & demand
20 Global data center demand is projected to nearly triple to 219 GW by 2030; ~70% of new demand is AI workloads.
21 AI-ready capacity is set to grow from ~54% of global data center capacity in 2025 (44GW of 82GW) to ~71% by 2030 (156GW of 219GW).
22 North America primary-market vacancy hit a record-low 1.4% in H1 2026; Northern Virginia sits at 0.2%.
23 80.4% of all primary-market data center space under construction is already preleased, up from 74.3% a year earlier.
Pricing
24 North American wholesale colocation for 250–500kW requirements is on pace to exceed $215/kW/month for full-year 2026, up from a H2 2025 record of $196/kW/month, as CBRE raised its outlook on record-low 1.4% vacancy.
25 Ashburn (Northern Virginia) wholesale rates for 10MW+ blocks averaged $173/kW/month (range $160–185) in H1 2026, up just 1.5% YoY — a sharp deceleration from H2 2025's record pace as record-low 0.2% vacancy collided with fewer large deals closing.
26 Singapore is Asia-Pacific's most expensive colocation market at $330–475/kW/month (avg ≈ $403).
27 A retail colocation rack (3–5 kW) in the US typically costs $500–1,500 per month.
Coloprice v1 aggregation
28 H100 on-demand rental spans $1.49–6.98/GPU·h (Q2 2026); 1-year contracts rebounded 40% to $2.35/GPU·h between Oct 2025 and Mar 2026.
Southeast Asia
29 Southeast Asia's data center market will grow from $15.72B (2025) to $35.08B by 2031 (14.32% CAGR).
ResearchAndMarkets, Southeast Asia Data Center Market Landscape 2026-2031
30 Thailand is the region's fastest-growing market: 0.77 GW (2025) to a projected 2.93 GW by 2030 (~30.6% CAGR).
31 Thailand's BOI approved a new record THB 958 billion (~$29B) of investment in May 2026 — six projects, three of them data centers, led by TikTok's $25B expansion.
32 TikTok/ByteDance's approved investment in Thai data centers has grown to roughly $25 billion — the largest project in the country.
33 Johor, Malaysia's data center market is now valued at $39.11B with a pipeline of 8,542 MW and colocation vacancy at just 0.7%; build costs reached $12M/MW.
34 From February 2026 Malaysia restricts new non-AI data centers over grid and water constraints — a window for Thailand and Vietnam.
35 Vietnam has Southeast Asia's cheapest data center construction at $6–8M per MW; a data-localization law takes effect Jan 1, 2026.
Power & energy
36 Big tech has contracted ~9.8 GW of nuclear capacity across 13 deals: Microsoft (Three Mile Island restart, 835 MW), Google (Kairos SMRs, 500 MW), Amazon (X-energy, up to 12 SMRs), Meta (5.2 GW), plus 2.2 GW from other data-center operators.
37 The first 'nuclear electrons' dedicated to AI data centers are expected in 2027 (Crane Clean Energy Center).
38 Grid connection — not floor space — is the binding constraint on new data center supply in every major market.
39 Modern AI halls are designed for 60–130+ kW per rack, making liquid cooling the default for new AI capacity.
Coloprice v1 aggregation
40 Thailand's commercial electricity rate is ~THB 4.20–4.55/kWh (≈ $0.12) — 15–20% above Malaysia and Vietnam. A separate green tariff (UGT2) for large users incl. data centers went live in March 2026 at ~THB 4.56/kWh, requiring a 10-year supply agreement with MEA/PEA.
How many data centers are there? →