Data Center Market Update: Week of October 5, 2026
CoreWeave books 240MW in Navi Mumbai, Digital Realty starts a 24MW Osaka building, Virtus closes £2.45B of debt, and Lombardy's council rejects 80MW.

Capacity announcements this week skewed to Asia and to financing: CoreWeave committed to 240MW in Navi Mumbai, Digital Realty began a 24MW building in Osaka, and Virtus raised £2.45 billion of debt for UK and European growth. In Lombardy, meanwhile, a council turned down an 80MW project outright, a reminder that consent risk is now priced alongside power.
Key takeaways
- CoreWeave announced 240MW across three 80MW buildings at AdaniConneX’s Taloja campus (Navi Mumbai) on 6 October; first capacity is not expected before mid-2028.
- Digital Realty and Mitsubishi’s joint venture started the 24MW KIX15 building in Osaka for Q4 2028, taking the venture’s Japan portfolio to about 220MW.
- Virtus closed a £2.45 billion (about $3.25 billion) 13-bank facility, including a £1.2 billion green capex tranche.
- Cologno Monzese’s council in Lombardy unanimously rejected an 80MW project; two other Lombardy proposals (120MW, 240MW) have been withdrawn or opposed.
- Legacy Investing and GI Partners are converting Chicago’s former Cboe headquarters to 33MW, a $40 million purchase that depends on existing ComEd power.
- Aterio’s October update separates gigawatt-scale plans from physical construction, a caution on headline pipeline numbers.
Asia-Pacific: India and Japan add AI-grade capacity
CoreWeave’s India announcement, dated 6 October 2026, covers 240MW in three 80MW buildings at the Taloja campus of AdaniConneX, the Adani Enterprises and EdgeConneX joint venture. Nvidia’s Vera Rubin platform is specified, CoreWeave is the sole tenant, and an option to double the campus to 480MW is not committed. The company has not disclosed financing, a building-by-building schedule or site-level power and water data, and first-phase capacity is not expected before mid-2028. It follows CoreWeave’s 360MW Indonesia plan announced in August, its first Asia-Pacific entry. For market context see our India data center market guide.
In Japan, Digital Realty announced on 7 October the start of construction on KIX15, a 24MW building at the KIX Campus in Ibaraki City, Osaka. It is built through MC Digital Realty, the 50/50 venture with Mitsubishi Corporation, is the campus’s fifth building, and is due to open in Q4 2028. Reports describe hybrid air and liquid cooling, seismic isolation and about 17,672 sqm of floor area. Earlier buildings include KIX12 at 20MW and KIX13 at 21MW.
| Project | Operator | Capacity | Stated timing |
|---|---|---|---|
| Taloja, Navi Mumbai | CoreWeave / AdaniConneX | 240MW (option to 480MW) | First capacity mid-2028 or later |
| KIX15, Osaka | Digital Realty / Mitsubishi JV | 24MW | Opens Q4 2028 |
Both projects deliver two years or more out. Buyers needing capacity before 2028 in either market are competing for existing inventory; our data center catalog lists operational facilities by country.
Financing: Virtus raises £2.45 billion
Virtus Data Centres closed a £2.45 billion debt package, reported at about $3.24–3.25 billion, from 13 banks. BNP Paribas, Crédit Agricole CIB, Société Générale and Standard Chartered coordinated. The facility includes a £1.2 billion green capex tranche and funds the 78MW Saunderton campus in Buckinghamshire, further work at LONDON19 in Slough and expansion in Germany, Italy and Spain. Virtus is majority-owned by Singapore’s STT GDC, with Macquarie Asset Management holding 40% since 2023.
The deal is consistent with the shift toward bank and structured financing for European platforms; track comparable announcements in our transactions tracker and investment hub.
Consent risk: Lombardy says no
The council of Cologno Monzese unanimously rejected an 80MW project from Officine Mak and 2C Sviluppo Immobiliare on a former industrial site, in a resolution dated 24 September. It cited water and electricity use, land footprint and technological waste as conflicting with municipal environmental goals, and gave up an expected €12 million in fees. East Gate withdrew a 120MW plan in Travagliato after about ten months, and a 240MW proposal in Magenta faces resident protests. Lombardy has adopted Regional Law No. 11/2026, Italy’s first comprehensive data center framework, aimed at sustainable development and brownfield reuse.
For developers and tenants, the lesson is that Milan-area pipeline figures include projects with unresolved local consent. Our Capacity Watch page records announced capacity as stated, not as delivered.
United States: conversions and what pipelines mean
In Chicago, Legacy Investing and GI Partners are converting the former Cboe headquarters at 400 S. LaSalle into a 33MW data center. The building was bought in fall 2025 for $40 million, after trading for $12 million a year earlier, and the key asset is an arranged ComEd power supply. Capacity is targeted for the end of 2026 or early 2027, depending on the report; building size is quoted inconsistently across outlets (300,500 or 385,000 sq ft).
Aterio’s October update, released 8 October and covering September, distinguishes plans from physical work. Amazon’s Homer City campus in Pennsylvania has 39 planned buildings with about 3.7GW allocated from a 4.5GW plant, phased 2030–2036. Fluidstack’s Harlingen, Texas campus of up to 1.5GW shows only site clearing in satellite imagery. Iowa’s Peosta proposal of 500–850MW of onsite gas generation is at concept stage with moratoria in place. Aterio warns that the plant rating and the campus allocation measure different things and should not be added.
GPU pricing
Coloprice’s tracker, last updated 28 September, shows the following on-demand medians per GPU-hour:
| Model | Median | Range |
|---|---|---|
| H100 | $3.29 | $1.30–12.29 |
| H200 | $4.40 | $2.09–13.78 |
| B200 | $6.25 | $3.69–16.11 |
| GB200 NVL72 | $13.25 | $8.00–27.04 |
Live data and history are on the GPU tracker.
What this means for capacity buyers
- Separate announced from deliverable. The week’s two largest Asian projects deliver in 2028 or later; contract only against dated, energized capacity.
- Check consent status line by line. Council rejections in Lombardy show that a site with land and a developer can still fail on environmental grounds.
- Prefer power-in-hand conversions for speed. Chicago’s 33MW conversion rests on an existing utility arrangement, not a new queue position; see our grid connection queues guide.
- Read financing as a delivery signal. A closed bank facility, like Virtus’s, is stronger evidence for a named campus than a pipeline headline.
- Benchmark before negotiating. Compare quotes against the Coloprice index and request pricing through the quote form.
常见问题
What did CoreWeave announce in India?
On 6 October 2026 CoreWeave announced a 240MW initial deployment across three 80MW buildings at AdaniConneX's Taloja campus in Navi Mumbai, with Nvidia's Vera Rubin platform. An option to double the campus to 480MW is not committed, and first capacity is not expected before mid-2028. Financing, anchor customers and power and water details were not disclosed.
What is Digital Realty building in Osaka?
On 7 October 2026 Digital Realty announced construction of KIX15, a 24MW building at the KIX Campus in Ibaraki City, Osaka, through its 50/50 joint venture with Mitsubishi Corporation. It is the fifth building on the campus, is due to open in Q4 2028, and would take the joint venture's Japan portfolio to 10 data centers and about 220MW of IT capacity.
How large is the Virtus financing?
Virtus Data Centres closed a £2.45 billion (about $3.25 billion) debt package from 13 banks, coordinated by BNP Paribas, Crédit Agricole CIB, Société Générale and Standard Chartered. It includes a £1.2 billion green capex facility and targets the 78MW Saunderton campus, LONDON19 in Slough and expansion in Germany, Italy and Spain.
Why did an Italian council reject an 80MW data center?
Cologno Monzese's council in Lombardy unanimously rejected an 80MW proposal by Officine Mak and 2C Sviluppo Immobiliare in a resolution dated 24 September 2026. It cited water and electricity use, land footprint and technological waste as conflicting with its environmental goals, forgoing an expected €12 million in fees.
What is happening with the former Cboe headquarters in Chicago?
Legacy Investing and GI Partners are converting the 400 S. LaSalle building into a 33MW data center. They bought it in fall 2025 for $40 million after a $12 million trade a year earlier; capacity is targeted for late 2026 or early 2027, depending on the report, and ComEd power supply was arranged by prior owners.
Where are GPU rental prices?
In Coloprice's tracker as of 28 September 2026 the median on-demand rate is $3.29/GPU-hour for H100 (range $1.30-12.29), $4.40 for H200, $6.25 for B200 and $13.25 for GB200 NVL72, whose floor is GMI Cloud's $8.00 listing.
资料来源
本文引用的一手来源。每个数字都链接到其出处。
- Remio: CoreWeave India data center bet puts 240MW against a 2028 deadline
- Datacentre Magazine: Digital Realty starts construction on KIX15 in Osaka, Japan
- Tech Coffee House: Digital Realty starts building 24MW Osaka data centre (8 October 2026)
- DataCenterDynamics: Virtus secures £2.45bn in financing for data center build-out
- Bisnow: UK data centre giant bags £2.45B debt facility
- DataCenterDynamics: Council rejects 80MW data center in northern Italy
- DataCenterDynamics: Legacy Investing, GI Partners announce 33MW data center in Chicago
- Aterio October 2026 US data center project stages (via asic.tools)
- Baxtel: Top data center news roundups
- Coloprice GPU price tracker, updated 28 September 2026