▮▮Coloprice

23 markets · as of · current month

Colocation Price Index: November 2026

Current month, updated as new benchmarks land. As of 2026-11-04 the Coloprice Colocation Price Index covers 23 markets with a published wholesale benchmark. The median is $200 per kW of committed IT load per month; the cheapest market is São Paulo at $160 and the most expensive is Singapore at $403. Versus the end of the previous month, 0 markets changed and 0 markets were added.

$200

median, per kW per month

$160

lowest · São Paulo

$403

highest · Singapore

0 / 0

markets moved / added vs previous month

Wholesale colocation by market, end of November 2026

MarketUSD / kW / monthvs previous monthAs ofBenchmark source
Singapore$403—CBRE, Global Data Center Trends 2026
Hong Kong$295—CBRE, Global Data Center Trends 2026 (17 June 2026)
Tokyo$280—CBRE, Global Data Center Trends 2026 (17 June 2026)
Querétaro$260—CBRE, Global Data Center Trends 2026 (17 June 2026)
Frankfurt$250—CBRE, Global Data Center Trends 2026 (17 June 2026)
Silicon Valley$238—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 1 — 250–500 kW asking rates
Chicago$215—CBRE, Global Data Center Trends 2026 (17 June 2026)
London$213—CBRE, Global Data Center Trends 2026 (17 June 2026), Fig. 5 — Q1 2026, 250–500 kW
Los Angeles (Southern California)$213—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 2 — secondary markets, 250–500 kW
New York Tri-State$213—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 1 — 250–500 kW asking rates
Hillsboro (Portland)$205—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 1 — 250–500 kW asking rates
Santiago$200—CBRE, Global Data Center Trends 2026 (17 June 2026)
North America (avg)$196—CBRE, North America Data Center Trends H2 2025
Phoenix$195—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 1 — 250–500 kW asking rates
Atlanta$193—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 1 — 250–500 kW asking rates
Bogotá$190—CBRE, Global Data Center Trends 2026 (17 June 2026)
Paris$190—CBRE, Global Data Center Trends 2026 (17 June 2026), Fig. 5 — Q1 2026, 250–500 kW
Sydney$188—CBRE, Global Data Center Trends 2026 (17 June 2026)
Amsterdam$180—CBRE, Global Data Center Trends 2026 (17 June 2026), Fig. 5 — Q1 2026, 250–500 kW
Houston$180—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 2 — secondary markets, 250–500 kW
Northern Virginia (Ashburn)$173—CBRE, North America Data Center Trends H1 2026 (10MW+ blocks)
Dallas–Fort Worth$173—CBRE, North America Data Center Trends H1 2026 (27 Aug 2026), Fig. 1 — 250–500 kW asking rates
São Paulo$160—CBRE, Global Data Center Trends 2026 (17 June 2026)

How to read this snapshot

Each row is the last published wholesale benchmark on or before the end of November 2026: committed IT load, USD per kW per month, excluding metered power. The “vs previous month” column compares with the last value on or before the end of the prior month; “new” means the market entered the index this month. Markets without a published benchmark are not listed. Wholesale = committed IT load, USD per kW per month, excluding metered power. Retail = per-rack (3–5 kW) monthly range. Markets marked “collecting” ship with the next quarterly release.

Series: price history · live table: the index · methodology: how prices are compiled.