Data center migration checklist

48 items across the six phases of a migration. Each one is here because leaving it out has a specific, recurring consequence — where that consequence is not obvious, it is written underneath. Tick state is stored in your browser; nothing is sent anywhere and there is no signup.

0 of 48 complete

01 Discovery and dependency mapping

4–8 weeks · owned by Infrastructure architecture · gate: A dependency graph signed off by application owners, with every system assigned to a move group.

02 Target site selection and design

6–12 weeks · owned by Infrastructure + procurement · gate: Signed colocation contract with commissioned space, power energised, and cross-connects ordered.

03 Network and connectivity build

8–16 weeks · owned by Network engineering · gate: Both sites live on the same L2/L3 fabric, tested at full bandwidth, with the temporary inter-site link in place.

04 Pilot wave

2–4 weeks · owned by Migration lead · gate: Pilot systems running in the target site for a full business cycle with no rollback and no unplanned outage.

05 Production waves

8–26 weeks · owned by Migration lead + application owners · gate: Each wave signed off by its application owner after a post-move validation pass.

06 Decommission and exit

4–12 weeks · owned by Facilities + procurement · gate: Written confirmation from the outgoing provider that the space is returned and billing has stopped.

Next

The checklist tells you what to do. The cost calculator tells you what it will cost, the cutover runbook covers the night itself, and the facility catalog plus certification directory narrow the target shortlist.