Stargate Norway (Nscale / Aker, Narvik)

Under construction

Stargate Norway (Nscale / Aker, Narvik) is a data center in Narvik, Norway, operated by Nscale / Aker (50/50 joint venture), with 230 MW of published IT capacity, currently under construction.

Nscale and Aker's AI campus at Kvandal near Narvik, announced July 2025 with OpenAI as initial customer, targets 230 MW with ambitions for 290 MW more, direct-to-chip liquid cooling and hydropower; press reports in April 2026 said OpenAI stepped back from the offtake and Microsoft took the capacity.

Stargate Norway (Nscale / Aker, Narvik) — schematic illustration
Schematic illustration based on published specifications, not a photograph · liquid-cooled · under construction

5 of 14 fields published · Operator? Add or correct data →

Units
City
Narvik, Norway
Power, MW
230 MW
Cooling
Liquid
AI-ready
Yes

2 sources · data pending on-site verification

—

Coloprice Score

22 out of 100

limited data · #15 of 35 in Norway

  • Resilience0/35
  • Compliance0/20
  • Transparency4/20
  • Scale15/15
  • Maturity3/10
How the score is calculated →
Embed score badge
Stargate Norway (Nscale / Aker, Narvik) — Coloprice Score 22
<a href="https://coloprice.com/data-centers/norway/narvik/nscale-aker-stargate-norway-narvik/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/nscale-aker-stargate-norway-narvik.svg"
    alt="Stargate Norway (Nscale / Aker, Narvik) — Coloprice Score 22" height="64">
</a>

Stargate Norway is an AI data center project at Kvandal, just outside Narvik in Northern Norway, announced on 31 July 2025 by Nscale, Aker and OpenAI. The announcement says the site is planned to deliver 230 MW of capacity with ambitions to add a further 290 MW, and that it targets 100,000 NVIDIA GPUs by the end of 2026. It is to be designed and built by Nscale and owned by a 50/50 joint venture between Nscale and Aker. The partners committed approximately USD 1 billion to the initial 20 MW phase, including upwards of USD 250 million in equity on a 100% basis. The operator cites abundant hydropower, low local demand and limited transmission capacity as the reasons for the location. In April 2026 trade press reported that OpenAI had pulled back from the offtake and that Microsoft was expected to take over the capacity; the original press release has not been updated for that change. Nscale's site list repeats the 230 MW design figure and the 290 MW expansion plan.

  • ▮Announced 31 July 2025: 230 MW planned, with ambitions for a further 290 MW.
  • ▮Initial 20 MW phase backed by approximately USD 1 billion in commitments from Nscale and Aker.
  • ▮Target of 100,000 NVIDIA GPUs by the end of 2026, per the announcement.
  • ▮Owned by a planned 50/50 Nscale–Aker joint venture; powered by renewable hydropower.
  • ▮April 2026 press reports say Microsoft is expected to take over capacity discussed with OpenAI.

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

Source — Verified against operator sources · data pending on-site verification

  • Nscale — Stargate Norway press release
  • w.media — Stargate pulls out of Norway data center deal as Microsoft takes over