Lambda Plans $33.1 Billion Red Clay AI Campus in Lowndes County, Alabama
On November 4, 2026 Lambda announced a $33.1B data center campus in Lowndes County, Alabama, with construction from Q1 2027 and first operations in Q4 2028.

Lambda, the GPU cloud provider, announced on November 4, 2026 that it plans to build a large-scale data center campus in Lowndes County, Alabama, an estimated $33.1 billion investment. The site, called the Red Clay Technology Center Campus, is being readied for development by Cloverleaf Infrastructure. Lambda expects construction to start in the first quarter of 2027 and to run for up to five years. Lambda’s own release does not give a megawatt figure.
What is known
According to Lambda’s press release, the project is expected to create more than 1,000 construction jobs and, once operating, support more than 225 full-time roles. The release cites Cloverleaf’s projection of more than $2.8 billion in local tax revenue through 2049, including more than $1.6 billion for Lowndes County Public Schools, and $3.4 billion combined state and local.
Power would come from Alabama Power, pending regulatory approval. DatacenterDynamics reports that the campus is planned at 1GW with potential to scale to 1.5GW, citing Cloverleaf’s project page, and that first operations are expected in Q4 2028. It also reports earlier plans for four data buildings of about 720,000 sq ft each on roughly 800 acres, near the junction of US Highway 80 and Alabama Highway 21, about six miles southwest of Montgomery. Lambda says final design details will be developed as planning progresses, so these figures are not confirmed by the company.
The $33.1 billion is Lambda’s estimate of total investment in Alabama. DatacenterDynamics quotes Cloverleaf’s agreement documents, in which the company agrees to use commercially reasonable efforts to invest at least $16 billion in aggregate capital investment within seven years of the placed-in-service date. The two numbers measure different things and should not be compared directly.
Lambda lists several commitments: paying the full cost of power and grid infrastructure through upfront financial commitments that apply even if plans change; closed-loop cooling, with a plan to return at least as much water as the facility uses via a partnership with N-Drip; setbacks, buffers and DarkSky lighting; and $10 million for a Community Benefits Agreement with the Central Alabama Community Foundation. GovTech reported that the Lowndes County Commission approved tax abatements for the project, totalling more than $1.1 billion, by a 3-2 vote; the project has drawn local opposition.
What this means for buyers of capacity
The announcement is a neocloud moving from leasing to developing its own campus. Lambda already appears in our GPU price tracker with H100 SXM list prices of $3.99–4.29 per GPU-hour, so the economics of owning shells versus renting them are now part of how the cloud prices its capacity. See our comparison of neoclouds and hyperscalers and the explainer on how AI data centers are financed.
For colocation buyers, a self-built gigawatt-class campus does not add to the leasable supply: it is capacity the developer will use itself. The first operations date of Q4 2028 means nothing arrives before then. Our US catalog lists only facilities documented in primary sources, and this campus will be added once there is a permitted or operating building to document. For the broader problem of waiting for power, see grid connection queues.
What we do not know yet
Lambda has not disclosed the campus megawatt capacity, the number or size of buildings, a tenant or customer commitments beyond its own use, or the financing structure behind the $33.1 billion estimate. Alabama Power’s regulatory approval is pending. Local opposition and the 3-2 county vote suggest that the permitting timeline could still change. The 1GW to 1.5GW and building-size figures come from Cloverleaf-sourced reporting, not from Lambda’s release.
Frequently asked questions
How big is Lambda's Alabama data center project?
Lambda said on November 4, 2026 that the Red Clay Technology Center Campus in Lowndes County represents an estimated $33.1 billion investment. Lambda's release does not state a megawatt figure; DatacenterDynamics, citing Cloverleaf Infrastructure's project page, reports 1GW with potential to scale to 1.5GW.
When will the Lowndes County campus be operational?
Lambda expects construction to begin in the first quarter of 2027 and to take up to five years. DatacenterDynamics reports first operations are expected in Q4 2028. Power from Alabama Power is still pending regulatory approval.
Who pays for the power and grid upgrades?
Lambda says it will pay the full cost of the power and grid infrastructure required to serve the facility through upfront financial commitments that apply even if project plans change, so costs are not shifted to existing Alabama Power customers.