Green Mountain OSL-Enebakk

Operational

Green Mountain OSL-Enebakk is a data center in Oslo (Enebakk), Norway, operated by Green Mountain, with 75 MW of published IT capacity, currently operational.

Green Mountain's Oslo-area campus in Enebakk, three buildings totaling 75 MW of site capacity fed by two independent hydropower grid connections.

Green Mountain OSL-Enebakk — schematic illustration
Schematic illustration based on published specifications, not a photograph · air-cooled · in operation

6 of 14 fields published · Operator? Add or correct data →

Units
City
Oslo (Enebakk), Norway
Power, MW
75 MW
Cooling
Air
Floor space
75,000 m²
AI-ready
Yes

1 sources · data pending on-site verification

—

Coloprice Score

27 out of 100

limited data · #10 of 35 in Norway

  • Resilience0/35
  • Compliance0/20
  • Transparency7/20
  • Scale13/15
  • Maturity7/10
How the score is calculated →
Embed score badge
Green Mountain OSL-Enebakk — Coloprice Score 27
<a href="https://coloprice.com/data-centers/norway/oslo/green-mountain-osl-enebakk-oslo/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/green-mountain-osl-enebakk-oslo.svg"
    alt="Green Mountain OSL-Enebakk — Coloprice Score 27" height="64">
</a>

Awards & badges

Earned from the rankings — position in the country, city, category and worldwide lists, plus score axes at their maximum. Free to embed on the operator's site; each badge links back to the list that certifies it.

Green Mountain OSL-Enebakk — Top 10 data centers in Norway 2026
#10 of 35 · See the list →
Green Mountain OSL-Enebakk — Top 10 data centers in Oslo (Fetsund), Norway 2026
#4 of 15 · See the list →

OSL-Enebakk is Green Mountain's campus roughly 20 km outside Oslo, built out in three phases as demand grew: an initial building opened in October 2020, a second 13.5 MW building followed in December 2022, and a third 10 MW building was added in 2024. Across all three, the operator states a site capacity of 75 MW with a stated line-of-sight capacity of 93 MW as the campus continues to expand, spread over roughly 75,000 sqm. The first building is single-tenant while the other two are multi-tenant colocation halls, giving Green Mountain a mix of hyperscale and enterprise customers on one site. Power is drawn from two independent hydropower-fed grid connections, a redundancy approach distinct from the diesel-generator backup common elsewhere in the Nordics, and cooling runs on an N+1 chiller design with an average PUE the operator states at 1.20. Unlike Green Mountain's Rennesoy and Rjukan campuses, which carry Uptime Institute Tier III certifications, no third-party certification is published for the Enebakk site specifically.

  • ▮Three buildings phased 2020/2022/2024, 75 MW site capacity
  • ▮75,000 sqm campus, two independent hydropower grid feeds
  • ▮N+1 chillers, average PUE cited at 1.20
  • ▮Mix of single-tenant and multi-tenant halls

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

More data centers in Oslo (Enebakk)

FacilityOperatorPower, MWTierStatus
Green Mountain OSL-EnebakkGreen Mountain75—Operational
STACK OSL03STACK Infrastructure22—Operational
STACK OSL04STACK Infrastructure18—Operational
Bulk Infrastructure OS-IXBulk Infrastructure14—Operational
Skygard OSL1Skygard20—Operational
Skygard OSL3Skygard3.6—Operational

Source — Verified against operator sources · data pending on-site verification