CX Technology Campus (Chapelcross)
AnnouncedCX Technology Campus (Chapelcross) is a data center in Annan (Chapelcross), United Kingdom, operated by CX Tech, with 1000 MW of published IT capacity, announced, not yet built.
Proposed ~1 GW data centre campus in eight buildings (up to 162,000 sqm) on 55 hectares north of the former Chapelcross nuclear station near Annan, Scotland; planning permission in principle was lodged in October 2026.

- Operator
- CX Tech
- City
- Annan (Chapelcross), United Kingdom
- Power, MW
- 1000 MW
- Cooling
- Air
- Market benchmark
- $213 per kW per month wholesale · United Kingdom
- Index rate for the market, not this operator’s price list
- Address
- Land north of former Chapelcross power station, near Annan, Dumfries and Galloway, Scotland · Open in maps ↗
2 sources · data pending on-site verification
Coloprice Score
17 out of 100
limited data · #107 of 196 in United Kingdom
- Resilience0/35
- Compliance0/20
- Transparency6/20
- Scale11/15
- Maturity0/10
Chapelcross, on the Solway coast near Annan, hosted a Cold War RAF station and later a nuclear power station that closed in 2004; CX Tech now proposes turning the brownfield land to its north into one of the largest data centre campuses in the UK. The company describes a 55-hectare site with eight data centre buildings totalling up to 162,000 sqm and roughly 1 GW of potential capacity, plus an on-site substation, industrial space and a training centre. Published design targets include closed-loop, non-evaporative air cooling with a PUE of 1.30 or better, and low water use. The site already has 132 kV electrical infrastructure, and SP Energy Networks completed a refurbishment of the Gretna–Chapelcross line in August 2026; the developer is also exploring private-wire links to nearby wind, solar and biomass generation. The investment is quoted at £16.5 billion, with an eight-year phased build that could start in 2027 if consent is granted. As of October 2026 only planning permission in principle has been filed and an environmental impact assessment is underway, so no tenants, power contracts or delivery dates are confirmed.
- ▮~1 GW potential capacity in eight buildings, up to 162,000 sqm
- ▮55-hectare brownfield site beside the former Chapelcross nuclear station
- ▮Closed-loop non-evaporative air cooling, target PUE 1.30 or better
- ▮Existing 132 kV infrastructure; private-wire renewables being explored
- ▮Planning permission in principle lodged October 2026; build 2027–2035 if approved
Colocation pricing: United Kingdom & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Colocation quotes in Annan (Chapelcross): free, reply within one business day
Get Quotes →Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
Source — Verified against operator sources · data pending on-site verification