AWS Glen Rose Campus (Comanche Peak)
AnnouncedAWS Glen Rose Campus (Comanche Peak) is a data center in Glen Rose, Texas, United States, operated by Amazon Web Services, with 1200 MW of published IT capacity, announced, not yet built.
Proposed Amazon Web Services data center campus on Vistra land next to the Comanche Peak nuclear plant in Somervell County, Texas, with a 1,200 MW load described in an ERCOT large-load review.

- Operator
- Amazon Web Services
- City
- Glen Rose, Texas, United States
- Power, MW
- 1200 MW
- Cooling
- Air
- Market benchmark
- $196 per kW per month wholesale · United States
- Index rate for the market, not this operator’s price list
- Address
- Comanche Peak area, Somervell County, TX
1 sources · last checked 2026-11-07 · data pending on-site verification
Coloprice Score
17 out of 100
limited data · #823 of 1349 in United States
- Resilience0/35
- Compliance0/20
- Transparency6/20
- Scale11/15
- Maturity0/10
Amazon Data Services, an Amazon affiliate, is pursuing a campus on Vistra property adjacent to the Comanche Peak nuclear plant near Glen Rose in Somervell County, Texas. Somervell County commissioners moved forward with a development agreement in late October 2026, subject to finalised lease terms. Trade reports put the site at about 435 acres and the investment at roughly 5 billion US dollars. The power arrangement is the notable part: ERCOT has recommended conditional approval of a net-metering arrangement between the proposed 1,200 MW campus and the 2,400 MW plant, filed with the Public Utility Commission of Texas as Docket 59399. The proposed energization schedule starts at 100 MW in the fourth quarter of 2027, reaches 800 MW by the fourth quarter of 2029 and the full 1,200 MW by the fourth quarter of 2031. The supply would come under a 20-year power purchase agreement with Vistra. The project has not started operating and approvals are pending, so the 1,200 MW figure is a grid-side load request rather than an operator-stated IT capacity.
- ▮Sited on Vistra land beside Comanche Peak nuclear plant
- ▮1,200 MW load in ERCOT large-load review, PUCT Docket 59399
- ▮Energization proposed from 100 MW in Q4 2027 to 1,200 MW by Q4 2031
- ▮About 435 acres and roughly 5 billion dollars reported
- ▮Approvals and lease terms still pending
Colocation pricing: United States & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Colocation quotes in Glen Rose, Texas: free, reply within one business day
Get Quotes →Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
Source — Verified against operator sources · data pending on-site verification
- DCD — Amazon looks to build large-scale data center campus next to nuclear plant in Texas