Compass Meridian Campus is a data center in Meridian, MS, United States, operated by Compass Datacenters, with 320 MW of published IT capacity, currently under construction.

An eight-building, eight-year hyperscale campus in Lauderdale County, Mississippi, Compass's entry into the Southeast and one of the largest data center projects announced in the state.

Compass Meridian Campus — schematic illustration
Schematic illustration based on published specifications, not a photograph · air-cooled · under construction
Operator
Compass Datacenters
City
Meridian, MS, United States
Power, MW
320 MW
Cooling
Air

Coloprice Score

18 out of 100

limited data · #474 of 574 in United States

  • Resilience0/35
  • Compliance0/20
  • Transparency4/20
  • Scale11/15
  • Maturity3/10
How the score is calculated →
Embed score badge
Compass Meridian Campus — Coloprice Score 18
<a href="https://coloprice.com/data-centers/usa/meridian/compass-meridian-ms/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/compass-meridian-ms.svg"
    alt="Compass Meridian Campus — Coloprice Score 18" height="64">
</a>

Compass Datacenters broke ground in early 2025 on a campus in the I-20/59 Industrial Park near Meridian, Mississippi, planned as eight data center buildings of roughly 40 MW of IT load and 250,000 sq ft each, for a total of about 320 MW across the site. Mississippi Power has committed to supplying approximately 500 MW to the development to leave headroom for the campus's power needs, and the Mississippi Development Authority has certified Compass as a data center operator, unlocking a ten-year state income and franchise tax exemption plus sales and use tax exemptions on construction materials and equipment. State and local officials put the project's investment at roughly $10 billion at full build-out, including tenants' own IT equipment, with construction phased over approximately eight years. The announcement frames Meridian as one of the largest hyperscale developments in the Southeast, but Compass has not disclosed individual tenants, a completion date for the first building, or any third-party certification for the campus.

  • Eight buildings planned, ~40 MW / 250,000 sq ft each, ~320 MW total
  • Mississippi Power committed to ~500 MW of supply capacity
  • ~$10 billion projected investment at full build-out over ~8 years
  • 10-year state tax exemption as a certified Mississippi data center operator

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

Source — Verified against operator sources · data pending on-site verification