EdgeCore Ashburn Campus (Sterling)
Under constructionMaries Road and Moran Road, Sterling, VA
EdgeCore Ashburn Campus (Sterling) is a data center in Sterling, United States, operated by EdgeCore Digital Infrastructure, with 114 MW of published IT capacity, currently under construction.
EdgeCore Digital Infrastructure's Ashburn-market campus on Maries Road and Moran Road in Sterling, two single-tenant hyperscale buildings totaling 114 MW critical IT load, engineered for liquid-to-liquid cooling of NVIDIA VR racks.

- Operator
- EdgeCore Digital Infrastructure
- City
- Sterling, United States
- Power, MW
- 114 MW
- Cooling
- Liquid
- Floor space
- 63,639 m²
- AI-ready
- Yes
Coloprice Score
27 out of 100
Class E · #285 of 574 in United States
- Resilience0/35
- Compliance0/20
- Transparency9/20
- Scale15/15
- Maturity3/10
EdgeCore Digital Infrastructure markets this 17-acre, two-building campus under its 'Ashburn' brand, though the site itself sits in Sterling on Maries and Moran roads, within Loudoun County's wider Data Center Alley cluster. The two data centers combine for 114 MW of critical IT load across roughly 685,000 sq ft, with initial delivery targeted for 2026. EdgeCore designs the campus as a single-tenant hyperscale product rather than retail colocation, engineered for liquid-to-liquid cooling that supports NVIDIA VR-class GPU racks alongside conventional air-cooled loads. The operator cites a water usage effectiveness rating below 0.01 L/kWh from its closed-loop chilled-water systems and air-cooled chillers, and says the buildings are designed to meet LEED specifications. EdgeCore, founded in 2017 and rebranded from EdgeCore Internet Real Estate in 2023, runs a small number of large campuses rather than a broad portfolio, with Ashburn/Sterling one of six current or planned US markets alongside Culpeper, Louisa County, Phoenix, Reno and Silicon Valley.
- ▮Two buildings, 114 MW combined critical IT load, ~685,000 sq ft
- ▮17-acre site on Maries Road/Moran Road, Sterling
- ▮Liquid-to-liquid cooling engineered for NVIDIA VR racks
- ▮WUE below 0.01 L/kWh, designed to meet LEED specifications
- ▮Single-tenant hyperscale model; initial delivery targeted 2026
Colocation pricing: United States & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
More data centers in Sterling
Source — Verified against operator sources · data pending on-site verification