Aligned LBB-01 (Project Caprock, Abernathy)

Under construction

1498 County Road 315, Abernathy, TX 79311

Aligned LBB-01 (Project Caprock, Abernathy) is a data center in Abernathy, United States, operated by Aligned Data Centers, with 540 MW of published IT capacity, currently under construction.

Groundbreaking site of Project Caprock, a planned 313-acre, 540 MW, six-building AI campus in Hale County near Abernathy, Texas; first building (LBB-01) targeted for Q1 2027.

Aligned LBB-01 (Project Caprock, Abernathy) — schematic illustration
Schematic illustration based on published specifications, not a photograph · liquid-cooled · under construction
Operator
Aligned Data Centers
City
Abernathy, United States
Power, MW
540 MW
Cooling
Liquid
Floor space
153,290 m²
AI-ready
Yes
E

Coloprice Score

27 out of 100

Class E · #279 of 574 in United States

  • Resilience0/35
  • Compliance0/20
  • Transparency9/20
  • Scale15/15
  • Maturity3/10
How the score is calculated →
Embed score badge
Aligned LBB-01 (Project Caprock, Abernathy) — Coloprice Score 27
<a href="https://coloprice.com/data-centers/usa/abernathy/aligned-lbb01-abernathy/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/aligned-lbb01-abernathy.svg"
    alt="Aligned LBB-01 (Project Caprock, Abernathy) — Coloprice Score 27" height="64">
</a>

Project Caprock is Aligned Data Centers’ entry into West Texas, breaking ground in Hale County just outside Abernathy in April 2026. The operator’s groundbreaking announcement describes a 313-acre campus planned for six buildings and roughly 1.65 million sq ft, reaching 540 MW of capacity at full build — among the largest single campus figures Aligned has disclosed anywhere in its portfolio. The first building, LBB-01, is expected to reach service by the first quarter of 2027. Aligned frames the campus around AI and HPC workloads, pairing DeltaFlow liquid cooling with an air-cooled heat-rejection system in a closed-loop design intended to handle GPU-class density from the outset. The press release cites Xcel Energy as the partner delivering dedicated electrical infrastructure and Ryan Companies as general contractor, with Aligned estimating roughly $5 billion in regional economic impact from the build-out. No certifications, per-building square footage, or rack-density figures have been published yet beyond the campus-level plan; those details are expected to follow as individual buildings near completion.

  • 313-acre, 6-building campus planned for 540 MW total
  • First building (LBB-01) targeted for service Q1 2027
  • DeltaFlow liquid cooling + air-cooled heat rejection, closed-loop
  • Xcel Energy dedicated electrical infrastructure partner
  • ~$5B estimated regional economic impact

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

Source — Verified against operator sources · data pending on-site verification