Flexential Portland - Hillsboro 5
Under constructionFlexential Portland - Hillsboro 5 is a data center in Portland (Hillsboro), United States, operated by Flexential, with 36 MW of published IT capacity, currently under construction.
A 358,000 sq ft, 36 MW Flexential building under construction at 4975 NE Starr Blvd in Hillsboro, next to the operator's existing Hillsboro 4 site, liquid-cooling-ready for up to 80+ kW per cabinet.

- Operator
- Flexential
- City
- Portland (Hillsboro), United States
- Power, MW
- 36 MW
- Cooling
- Liquid
- Floor space
- 33,259 m²
- Market benchmark
- $196 per kW per month wholesale · United States
- Index rate for the market, not this operator’s price list
- Address
- 4975 NE Starr Blvd, Hillsboro, OR 97124, United States · Open in maps ↗
2 sources · data pending on-site verification
Coloprice Score
25 out of 100
Class E · #533 of 1344 in United States
- Resilience0/35
- Compliance0/20
- Transparency9/20
- Scale13/15
- Maturity3/10
Connectivity: 10 networks and 1 internet exchanges are present in this facility.
Awards & badges
Earned from the rankings — position in the country, city, category and worldwide lists, plus score axes at their maximum. Free to embed on the operator's site; each badge links back to the list that certifies it.
Flexential's Hillsboro 5 building, at 4975 NE Starr Boulevard, is under construction immediately next to the operator's existing Hillsboro 4 facility in Oregon's Silicon Forest submarket west of Portland. The building is designed for 358,000 sq ft and 36 MW of critical power on a 5:4 distributed-redundant UPS configuration with N+2 cooling, targeting a 1.4 power usage effectiveness once operational. Flexential positions the site as liquid-cooling-ready for up to 80+ kW per cabinet, aimed at AI and high-performance-computing tenants rather than conventional enterprise colocation loads — the same positioning the operator has used for its newer-generation buildings in Atlanta, Denver and Dallas. A September 2025 press release announcing a sixth Hillsboro building described Hillsboro 5 as already under construction and expected to come online the following year, and Flexential's August 2026 $800 million financing release again listed it among projects underway. No third-party Uptime Institute or TIA-942 certification, general contractor, or confirmed energization date is published for the building.
- ▮358,000 sq ft, 36 MW building under construction next to Hillsboro 4
- ▮5:4 distributed-redundant UPS, N+2 cooling, target 1.4 PUE
- ▮Liquid-cooling-ready for 80+ kW per cabinet (AI/HPC positioning)
- ▮Referenced as under construction in Flexential's Sept 2025 and Aug 2026 releases
- ▮Fifth Flexential-branded building in the Hillsboro/Portland cluster
Colocation pricing: United States & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Colocation quotes in Portland (Hillsboro): free, reply within one business day
Get Quotes →Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
More data centers in Portland (Hillsboro)
| Facility | Operator | Power, MW | Tier | Status |
|---|---|---|---|---|
| Flexential Portland - Hillsboro 5 | Flexential | 36 | — | Under construction |
| PDX10 | Digital Realty | — | — | Operational |
| PDX12 | Digital Realty | — | — | Operational |
| NTT Hillsboro HI1 Data Center | NTT Global Data Centers | 36 | — | Operational |
| QTS Hillsboro 2 | QTS Data Centers | 180 | — | Operational |
| QTS Hillsboro 1 | QTS Data Centers | 20 | — | Operational |
Source — Verified against operator sources · data pending on-site verification