Under constructionShippingport Industrial Park, Shippingport, PA (Beaver County)
Aligned Data Centers Project Phoenix is a data center in Shippingport, Pennsylvania, United States, operated by Aligned Data Centers, with 2000 MW of published IT capacity, currently under construction.
2 GW, three-building hyperscale AI/HPC campus breaking ground on the former Bruce Mansfield coal-plant site in Shippingport, Pennsylvania, powered behind-the-meter by an adjacent 3.6 GW natural-gas plant.

- Operator
- Aligned Data Centers
- City
- Shippingport, Pennsylvania, United States
- Power, MW
- 2000 MW
- Cooling
- Air
- AI-ready
- Yes
Coloprice Score
22 out of 100
limited data · #516 of 837 in United States
- Resilience0/35
- Compliance0/20
- Transparency6/20
- Scale13/15
- Maturity3/10
Aligned Data Centers broke ground on Project Phoenix on September 10, 2026, redeveloping the shuttered 660-acre Bruce Mansfield coal-plant site in Shippingport, Beaver County, roughly 25 miles northwest of Pittsburgh, into a three-building, 2 GW hyperscale AI and HPC campus. Each of the three planned data center buildings spans over 600,000 sq ft, and the site sits directly beside a newly converted 3.6 GW natural-gas power station that Aligned and partner Frontier Group of Companies are redeveloping in tandem, giving the campus dedicated behind-the-meter generation rather than a draw on the regional grid. Aligned says the arrangement should ultimately return surplus capacity to PJM, the grid operator serving Pennsylvania and much of the mid-Atlantic, rather than compete with residential and industrial load for scarce interconnection. The facility's cooling design uses a closed-loop system built around recycled, deionized water, which Aligned says keeps ongoing operational water draw comparable to a standard office building rather than a conventional evaporative-cooled data center. Construction is expected to support roughly 3,000 jobs on site and about 640 permanent operating roles once complete, anchoring an estimated $10 billion in regional investment; no completion date for the first building has been published.
- ▮Groundbreaking September 10, 2026 on the former Bruce Mansfield coal-plant site, Beaver County
- ▮2 GW planned across three buildings, each over 600,000 sq ft
- ▮Behind-the-meter power from an adjacent 3.6 GW natural-gas plant, not the local grid
- ▮Closed-loop deionized-water cooling; operational water use comparable to a standard office building
- ▮~3,000 construction jobs and ~640 permanent roles; $10B estimated regional investment
Colocation pricing: United States & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
Source — Verified against operator sources · data pending on-site verification