Market comparison
Osasco, Brazil vs São Paulo, Brazil
Both columns are built from the catalog and the price index: Osasco — 9 facilities from 2 operators, São Paulo — 10 facilities from 9 operators. Where a benchmark or a tariff is not published, the cell says so.
Osasco, Brazil
9
Tracked facilities · Operators: 2
Wholesale benchmark, $/kW/month: $160 (country-level)
São Paulo, Brazil
10
Tracked facilities · Operators: 9
Wholesale benchmark, $/kW/month: $160 (country-level)
Markets side by side
| Field | Osasco | São Paulo |
|---|---|---|
| Tracked facilities | 9 | 10 |
| Operators | 2 | 9 |
| Published IT capacity | 101 MW (9 of 9 sites publish) | 313 MW (4 of 10 sites publish) |
| Operational | 8 | 9 |
| Under construction / announced | 1 | 1 |
| Tier III+ certified sites | 6 | 5 |
| Sites with any certification | 6 | 5 |
| Liquid-cooled sites | 1 | 0 |
| AI-ready sites | 1 | 0 |
| Wholesale benchmark, $/kW/month | $160 (country-level) | $160 (country-level) |
| Benchmark change, yoy | 0% | 0% |
| Industrial power tariff, $/kWh | $0.152 | $0.152 |
| Average Coloprice Score | 42/100 across 9 sites | 23/100 across 10 sites |
| Latency between the two | not published | |
Counts are the Coloprice catalog as of 2026-09-26; benchmarks are the Colocation Price Index (Q3 2026). Operators publish some facts and not others — an empty cell means «not published», not zero.
Where they differ
Only fields both sides publish and where the values are not identical. This is not a judgement: the right choice depends on the workload, the contract and the site.
- Tracked facilities: Osasco — 9; São Paulo — 10
- Operators: Osasco — 2; São Paulo — 9
- Published IT capacity: Osasco — 101 MW (9 of 9 sites publish); São Paulo — 313 MW (4 of 10 sites publish)
- Operational: Osasco — 8; São Paulo — 9
- Tier III+ certified sites: Osasco — 6; São Paulo — 5
- Sites with any certification: Osasco — 6; São Paulo — 5
- Liquid-cooled sites: Osasco — 1; São Paulo — 0
- AI-ready sites: Osasco — 1; São Paulo — 0
- Average Coloprice Score: Osasco — 42/100 across 9 sites; São Paulo — 23/100 across 10 sites
Top facilities by score
Osasco, Brazil
- Ascenty São Paulo 5 Ascenty (Digital Realty) · 8 MW
- Ascenty São Paulo 2 Ascenty (Digital Realty) · 14 MW
- Ascenty São Paulo 6 Ascenty (Digital Realty) · 18 MW
São Paulo, Brazil
- HostDime Cotia (São Paulo) HostDime · 5.9 MW
- Mundi Data I Mundi Data Tecnologia em Informação
- Takoda SP01 Takoda Data Centers
Open Osasco data centers →Open São Paulo data centers →Colocation pricing in Osasco →Colocation pricing in São Paulo →