Operational

DigiCo SYD1 is a data center in Sydney, Australia, operated by DigiCo REIT, with 36 MW of published IT capacity, currently operational.

DigiCo REIT SYD1 comprises two adjoining data centre sites less than 1 km from the Sydney CBD, with 36 MW of installed IT capacity and 88 MW planned IT capacity according to the operator.

DigiCo SYD1 — schematic illustration
Schematic illustration based on published specifications, not a photograph · air-cooled · in operation

5 of 14 fields published · Operator? Add or correct data →

Units
Operator
DigiCo REIT
City
Sydney, Australia
Power, MW
36 MW
Cooling
Air
Market benchmark
$188 per kW per month wholesale · Sydney, Australia
Index rate for the market, not this operator’s price list

2 sources · data pending on-site verification

—

Coloprice Score

22 out of 100

limited data · #82 of 168 in Australia

  • Resilience0/35
  • Compliance0/20
  • Transparency4/20
  • Scale11/15
  • Maturity7/10
How the score is calculated →
Embed score badge
DigiCo SYD1 — Coloprice Score 22
<a href="https://coloprice.com/data-centers/australia/sydney/digico-syd1-sydney/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/digico-syd1-sydney.svg"
    alt="DigiCo SYD1 — Coloprice Score 22" height="64">
</a>

SYD1 is DigiCo REIT's Sydney campus, made up of two adjoining data centre sites less than one kilometre from the Sydney CBD. The operator describes it as the only large-scale data centre campus in the densely connected CBD and one of the largest in Australia, placed close to telecommunications exchanges, submarine cable points of presence and the city's financial and commercial districts, and operating as a carrier-neutral colocation site. DigiCo states an installed IT capacity of 36 MW and a planned IT capacity of 88 MW, so more than half of the planned load is not yet installed. The operator's location page does not publish a street address for the campus, floor area, rack count, rack density, cooling design or certifications, and these fields are left empty. The page cites land scarcity and limited power availability as barriers to entry in the Sydney metro market. Megaport also lists the site as an enabled location.

  • ▮Installed IT capacity of 36 MW, with 88 MW planned, per the operator.
  • ▮Two adjoining sites less than 1 km from the Sydney CBD.
  • ▮Described by the operator as the only large-scale campus in the CBD.
  • ▮Carrier-neutral, near telecom exchanges and submarine cable points of presence.
  • ▮Floor area, racks, density and certifications are not published.

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

More data centers in Sydney

FacilityOperatorPower, MWTierStatus
DigiCo SYD1DigiCo REIT36—Operational
AirTrunk SYD1 Sydney WestAirTrunk130—Operational
CDC Eastern Creek CampusCDC Data Centres200—Operational
Equinix SY5Equinix——Operational
Macquarie IC3 Super WestMacquarie Data Centres47—Under construction
NEXTDC S3 SydneyNEXTDC80IVOperational

Source — Verified against operator sources · data pending on-site verification