Ada Infrastructure Tokyo West 1 (TKW1)
OperationalAda Infrastructure Tokyo West 1 (TKW1) is a data center (Uptime Tier III, design certified) in Tokyo (West), Japan, operated by Ada Infrastructure, with 31 MW of published IT capacity, currently operational.
31 MW, three-building campus about 34 km from central Tokyo, developed by Ada Infrastructure (backed by Ares Management), with the first 10 MW building customer-ready from May 2025.

- Operator
- Ada Infrastructure
- City
- Tokyo (West), Japan
- Power, MW
- 31 MW
- Cooling
- Air
- Uptime Tier
- III · design certified
- AI-ready
- Yes
Coloprice Score
40 out of 100
Class D · #6 of 76 in Japan
- Resilience16/35
- Compliance0/20
- Transparency4/20
- Scale13/15
- Maturity7/10
Awards & badges
Earned from the rankings — position in the country, city, category and worldwide lists, plus score axes at their maximum. Free to embed on the operator's site; each badge links back to the list that certifies it.
Tokyo West 1 is the first campus Ada Infrastructure brought to market in Japan, part of a broader push by the Ares Management-backed developer into hyperscale and AI-oriented capacity across Tokyo and Osaka. The site sits roughly 34 km from Tokyo's central business district in one of the metro area's established data center corridors, with land owned outright and a dual-fed on-site substation carrying 50 MVA of secured power from TEPCO. The campus is built out as three three-story buildings of about 10 MW each for a total of 31 MW of IT load. Building 1 (TKW1-1) was developed first, split into two 5 MW phases, with the first data hall customer-ready from May 2025 and the building's Design Documents certified Uptime Institute Tier III. Buildings 2 and 3 are being delivered in smaller phases from 2027 and are built to be liquid-cooling ready for high-density AI hardware. The operator targets a 1.37 annualized design PUE with zero water used for cooling (WUE=0) across the campus.
- ▮31 MW campus across three 3-story buildings, about 10 MW each
- ▮Building 1 (TKW1-1) first 5 MW data hall customer-ready from May 2025
- ▮On-site substation with 50 MVA of secured power from TEPCO
- ▮Designed PUE 1.37 (annualized average), WUE=0 — no evaporative cooling
- ▮Uptime Institute Tier III Certification of Design Documents for TKW1-1
Colocation pricing: Japan & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
More data centers in Tokyo (West)
Source — Verified against operator sources · data pending on-site verification