▮▮Coloprice

Digital Edge TYO7

Under construction

Digital Edge TYO7 is a data center in Tokyo, Japan, operated by Digital Edge, with 4.8 MW of published IT capacity, currently under construction.

Interconnection-focused Digital Edge facility under development in Tokyo's Nihonbashi-Kobuna-cho district, planned for 4.8 MW across 970 cabinets less than 300 meters from the operator's existing TYO2 site.

Digital Edge TYO7 — schematic illustration
Schematic illustration based on published specifications, not a photograph · air-cooled · under construction

8 of 14 fields published · Operator? Add or correct data →

Units
Operator
Digital Edge
City
Tokyo, Japan
Power, MW
4.8 MW
Cooling
Air
Floor space
2,624 m²
Racks
970
Market benchmark
$280 per kW per month wholesale · Tokyo (Inzai), Japan
Index rate for the market, not this operator’s price list
Address
1-1 Nihonbashikobunacho, Chuo-ku, Tokyo 103-0024, Japan

1 sources · data pending on-site verification

E

Coloprice Score

23 out of 100

Class E · #55 of 150 in Japan

  • Resilience0/35
  • Compliance0/20
  • Transparency12/20
  • Scale8/15
  • Maturity3/10
How the score is calculated →
Embed score badge
Digital Edge TYO7 — Coloprice Score 23
<a href="https://coloprice.com/data-centers/japan/tokyo/digital-edge-tyo7-tokyo/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/digital-edge-tyo7-tokyo.svg"
    alt="Digital Edge TYO7 — Coloprice Score 23" height="64">
</a>

TYO7 is an interconnection-focused facility under development in the Nihonbashi-Kobuna-cho district of Tokyo's Chuo ward, about a kilometer from Otemachi — Japan's central network hub — and less than 300 meters from Digital Edge's existing TYO2 building. The eight-story, purpose-built structure is designed for 2,624 square meters of colocation space across 970 cabinets at 5 kVA each, with a seismic-isolated structure and a raised first floor as flood mitigation. Planned power infrastructure includes three utility feeders from a shared substation, N+1 primary UPS (four 1,200 kVA units plus a catcher UPS), and three 4,500 kVA gas turbine generators in N+1 configuration, targeting a designed annual PUE of 1.31. Digital Edge's published specification sheet, dated November 2024, describes the building as planned with a targeted Ready-for-Service date of Q2 2025 and lists ISO 14001, 27001, 45001 and LEED Silver certifications as pending rather than obtained. The operator positions TYO7 as a natural extension for existing TYO2 customers and for carriers and enterprises expanding their Tokyo footprint.

  • ▮4.8 MW planned IT capacity across 970 cabinets, 2,624 sqm
  • ▮Less than 300m from Digital Edge's existing TYO2 facility
  • ▮Seismic-isolated structure with flood-mitigation raised ground floor
  • ▮Targeted design PUE 1.31; ISO and LEED Silver certifications still pending

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

More data centers in Tokyo

FacilityOperatorPower, MWTierStatus
Digital Edge TYO7Digital Edge4.8—Under construction
AirTrunk TOK1 Tokyo EastAirTrunk300—Operational
Colt DCS Tokyo Inzai 4Colt DCS20—Operational
Digital Edge TYO2Digital Edge——Operational
Equinix TY12xEquinix54—Operational
Equinix TY1Equinix——Operational

Source — Verified against operator sources · data pending on-site verification

  • Digital Edge — TYO7 Tokyo Data Center