25 facilities · 11 operators · 85 MW tracked
Colocation in Santiago: pricing, providers and capacity
11 operators run 25 tracked data centers in Santiago (25 operational, 85+ MW published, 0 AI-ready). Below: the published price benchmark for this market, retail list prices where operators publish them, who owns capacity here, and how to get comparable quotes. Catalog data from primary sources; no estimates.
How much does colocation cost in Santiago?
11 operators run 25 tracked data centers in Santiago; the largest by sites is GTD (7). There is no city-level benchmark for Santiago; the closest published wholesale figure is Santiago at $200 per kW per month (CBRE, Global Data Center Trends 2026 (17 June 2026), H2 2025 – Q2 2026). No operator in this market publishes a retail rate card; prices are quoted on request.
Wholesale benchmark
$200 /kW·mo
Santiago · CBRE, Global Data Center Trends 2026 (17 June 2026) · H2 2025 – Q2 2026 · country-level benchmark, no city figure published
Published retail prices
No operator in Santiago publishes a retail rate card on its website. That is normal for wholesale-led markets and says nothing about price level — request quotes with one brief.
Colocation providers in Santiago
Operators with tracked data centers in Santiago, sorted by sites, then published capacity. Sites / operational; MW is the sum of what each operator publishes for these sites. Some entries are hyperscaler or enterprise sites that do not sell colocation — check the facility card.
| Operator | Sites / live | Published MW | Top-scored facility | Certifications | AI-ready |
|---|---|---|---|---|---|
| GTD | 7 / 7 | 8 | GTD Panamericana | Uptime Institute Tier III Certification of Design Documents, Uptime Institute Tier III Certification of Constructed Facility, Uptime Institute Gold Certification of Operational Sustainability | — |
| Equinix | 4 / 4 | not published | Equinix ST2 IBX | Uptime Institute Tier III Certification of Design Documents, Uptime Institute Tier III Certification of Constructed Facility, Uptime Institute Gold Certification of Operational Sustainability | — |
| Ascenty (Digital Realty) | 3 / 3 | 42 | Ascenty Santiago 2 | ISO 27001, PCI-DSS, SOC 1 Type II | — |
| EdgeConneX | 2 / 2 | 21 | EdgeConneX SCL02 | not published | — |
| SONDA S.A. | 2 / 2 | 12 | DC SONDA Kudos | Uptime Institute Tier IV Gold Certification of Operational Sustainability, Uptime Institute Tier IV Certification of Design Documents, ISO 27001 | — |
| NextStream | 2 / 2 | 2 | Data Center Apoquindo | Uptime Institute Tier III Certification of Design Documents, Uptime Institute Tier III Certification of Constructed Facility | — |
| Claro Chile (América Móvil) | 1 / 1 | not published | Claro Chile Liray — Etapa B5 | Uptime Institute Tier IV Certification of Design Documents, Uptime Institute Tier IV Certification of Constructed Facility | — |
| Ingeniería e Informática Asociada Ltda. (IIA) | 1 / 1 | not published | DC Porvenir (IIA) | Uptime Institute Tier III Certification of Design Documents | — |
| S&A Consultores Asociados Chile S.A. | 1 / 1 | not published | Data Center S&A Chile | Uptime Institute Tier III Certification, ISO 9001:2015, ISO/IEC 20000-1:2011 | — |
| Siptel Chile S.A. | 1 / 1 | not published | DC Siptel Balmoral I | Uptime Institute Tier III Certification of Design Documents | — |
| UFINET Chile SpA | 1 / 1 | not published | Magnus II | Uptime Institute Tier III Certification of Design Documents, Uptime Institute Tier III Certification of Constructed Facility | — |
Availability in Santiago: what the numbers do and do not say
Published megawatts describe how facilities are designed, not how much power is available to a new customer today. Vacancy is confirmed only in an operator's proposal for a specific hall and ready-for-service date. Where operators have told Coloprice that a market is sold out to a date, the facility cards say so; otherwise assume nothing and ask each provider the same question.
What the colocation price includes — and what it does not
- Included in the base fee: rack or cabinet space, a committed power circuit, cooling, physical security, and usually a basic remote-hands allowance.
- Billed separately: metered electricity above the allowance (or a per-kWh rate on retail contracts), cross-connects, IP transit, additional remote hands, and one-off setup or installation fees.
- Wholesale contracts add annual escalators, ramp schedules and power-commitment minimums; retail contracts add overage rates and bandwidth caps. Compare providers on the same committed kW, density, term and connectivity.
See also
Weekly digest: price moves, capacity and deals in one email.
FAQ
Who are the largest colocation providers in Santiago?
By tracked sites: GTD with 7. By published IT capacity: Ascenty (Digital Realty) with 42 MW. Facility counts and MW come from operator pages and registries; the table above lists every operator with a tracked site in Santiago, including some that do not sell space.
Is there colocation capacity available in Santiago right now?
Coloprice tracks 25 facilities here (25 operational, 0 under construction or announced) but does not track vacancy. Availability, rack density and delivery dates are confirmed only in a current proposal for a specific hall — send the same brief to several providers and compare.
How do I get comparable colocation quotes in Santiago?
Send every provider one brief: committed kW, density per rack, redundancy, carriers and cloud on-ramps, start date, term and expansion rights. Ask for space, power, metered electricity, cross-connects, installation and remote hands as separate lines, then compare against the Santiago benchmark. The form below routes one brief to matching operators; no operator pays for position.
Get colocation quotes in Santiago
One brief, several operators with capacity in Santiago, Chile, same terms. Independent — no operator pays for position.
Colocation in Santiago? One brief, several quotes.
Request quotes →