NorthC Frankfurt FRA01

Under construction

NorthC Frankfurt FRA01 is a data center in Frankfurt, Germany, operated by NorthC, with 6 MW of published IT capacity, currently under construction.

6 MW data center under construction at Mainzer Landstraße 695 in western Frankfurt, NorthC's fourth facility in the market, with the first phase due to go live in January 2028.

NorthC Frankfurt FRA01 — schematic illustration
Schematic illustration based on published specifications, not a photograph · air-cooled · under construction

5 of 14 fields published · Operator? Add or correct data →

Units
Operator
NorthC
City
Frankfurt, Germany
Power, MW
6 MW
Cooling
Air
Market benchmark
$250 per kW per month wholesale · Frankfurt, Germany
Index rate for the market, not this operator’s price list
Address
Mainzer Landstraße 695, Frankfurt am Main, Germany · Open in maps ↗

1 sources · data pending on-site verification

—

Coloprice Score

18 out of 100

limited data · #101 of 274 in Germany

  • Resilience0/35
  • Compliance0/20
  • Transparency6/20
  • Scale9/15
  • Maturity3/10
How the score is calculated →
Embed score badge
NorthC Frankfurt FRA01 — Coloprice Score 18
<a href="https://coloprice.com/data-centers/germany/frankfurt/northc-frankfurt-fra01/?utm_source=score-badge&utm_medium=embed">
  <img src="https://coloprice.com/badge/score/northc-frankfurt-fra01.svg"
    alt="NorthC Frankfurt FRA01 — Coloprice Score 18" height="64">
</a>

NorthC began preparatory construction work in September 2026 on FRA01, a new 6 MW data center at Mainzer Landstraße 695 in western Frankfurt. The project adds a fourth Frankfurt-area site to NorthC's portfolio alongside the operational Frankfurt 3 facility and a separate Frankfurt 2 project planned for nearby Neu-Isenburg, continuing the operator's build-out of the German market it entered through acquisitions in 2022. NorthC has not published cooling technology, certification targets or investment figures for FRA01, and the company's public statements describe only the site address, the 6 MW design capacity and a first-phase go-live date of January 2028. Frankfurt remains continental Europe's largest colocation and interconnection hub, anchored by the DE-CIX internet exchange, and continues to draw new supply from both hyperscale and multi-tenant operators despite periodically tight grid-connection availability in the region; NorthC's FRA01 adds incremental multi-tenant capacity to that market rather than a hyperscale campus.

  • ▮Preparatory construction began September 2026
  • ▮6 MW design capacity at Mainzer Landstraße 695, western Frankfurt
  • ▮First phase scheduled to go live January 2028
  • ▮NorthC's fourth Frankfurt-area site alongside operational Frankfurt 3

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.

Customer reviews

No reviews yet

Be the first to review — for current or former customers, work email required.

Write a review

Write a review

For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.

Your ratings
Uptime & reliability
Support & remote hands
Connectivity & cross-connects
Value for money
Onboarding & contract

Review guidelines →

Operate this facility? Get your free "Listed on Coloprice" badge →

Data release:

More data centers in Frankfurt

FacilityOperatorPower, MWTierStatus
NorthC Frankfurt FRA01NorthC6—Under construction
Colt DCS Frankfurt 3 Data CentreColt DCS32.4—Under construction
Colt DCS Frankfurt City Data CentreColt DCS——Operational
CyrusOne FRA3CyrusOne22—Operational
CyrusOne FRA7CyrusOne81—Under construction
Digital Realty FRA11Digital Realty (Interxion)——Operational

Source — Verified against operator sources · data pending on-site verification