Empyrion MY1 Johor Data Centre Campus
Under constructionSiLC Industrial Cluster, Nusajaya, Iskandar Puteri, Johor, Malaysia
Empyrion MY1 Johor Data Centre Campus is a data center in Iskandar Puteri (Nusajaya, SiLC), Malaysia, operated by Empyrion Digital, with 200 MW of published IT capacity, currently under construction.
First 40 MW building of Empyrion Digital's five-phase, 200+ MW hyperscale campus in Nusajaya, Johor topped out in August 2026, targeting Q1 2027 ready-for-service with liquid cooling below 1.3 PUE.

- Operator
- Empyrion Digital
- City
- Iskandar Puteri (Nusajaya, SiLC), Malaysia
- Power, MW
- 200 MW
- Cooling
- Liquid
- AI-ready
- Yes
Coloprice Score
24 out of 100
limited data · #22 of 64 in Malaysia
- Resilience0/35
- Compliance0/20
- Transparency6/20
- Scale15/15
- Maturity3/10
Awards & badges
Earned from the rankings — position in the country, city, category and worldwide lists, plus score axes at their maximum. Free to embed on the operator's site; each badge links back to the list that certifies it.
Empyrion Digital, a Singapore-headquartered platform backed by Seraya Partners, topped out the first 40 MW building of its MY1 campus in the SiLC industrial cluster of Nusajaya, Johor, in August 2026 — a construction milestone on the way to a five-phase, 200+ MW hyperscale campus on 34.9 acres. Tenaga Nasional Berhad has approved 145 MW of initial power allocation for the site, which is designed to hit a PUE below 1.3 on liquid cooling and below 1.4 on air cooling, targeting hyperscalers and AI/HPC tenants alongside conventional cloud workloads. First energisation is slated for September 2026, with the initial 40 MW building's ready-for-service date pushed from an original Q4 2026 target to Q1 2027. The campus is planned to connect to Singapore via the SPTel cross-border fiber platform, reinforcing Johor's role as overflow capacity for space- and power-constrained Singapore, and Empyrion intends to source green energy through long-term power purchase agreements. MY1 is Empyrion's sixth data center development across Asia and its first ground-up build in Malaysia, adding another entrant to the fast-growing SiLC and Iskandar Puteri corridor alongside Bridge, STT, AirTrunk and Equinix campuses already under construction nearby.
- ▮First 40 MW building topped out August 2026; RFS slipped to Q1 2027
- ▮Five-phase campus targeting 200+ MW on 34.9 acres in Nusajaya's SiLC cluster
- ▮145 MW initial TNB power allocation; PUE below 1.3 on liquid cooling
- ▮Planned SPTel cross-border fiber link to Singapore
- ▮Empyrion Digital's sixth Asian data center, first in Malaysia
Colocation pricing: Malaysia & other markets — The Colocation Price Index →
Get Quotes
Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.
Customer reviews
No reviews yet
Be the first to review — for current or former customers, work email required.
Write a review
For current or former customers of this facility. We verify the work email and publish only your role and company — never the email. Text is edited for spelling only.
Operate this facility? Get your free "Listed on Coloprice" badge →
Data release:
More data centers in Iskandar Puteri (Nusajaya, SiLC)
Source — Verified against operator sources · data pending on-site verification