Oracle Invokes Force Majeure on Stargate's Project Jupiter as New Mexico Pipeline Slips to 2027

Oracle notified developer Stack Infrastructure on September 24 that it may defer rent on the 2.45GW Project Jupiter campus if a stalled gas pipeline delays power past 2028.

Oracle Invokes Force Majeure on Stargate's Project Jupiter as New Mexico Pipeline Slips to 2027

On September 24, 2026, Oracle sent developer Stack Infrastructure — owned by Blue Owl Capital — a force majeure notice covering Project Jupiter, the 2.45-gigawatt data center campus it is building near Santa Teresa, New Mexico as one of the anchor sites of the Stargate program with OpenAI and SoftBank. Per Bloomberg’s reporting, confirmed by statements from both companies to other outlets, the notice preserves Oracle’s contractual right to defer rent payments for up to three years if the campus’s power infrastructure is not ready when the site is due to open in 2028.

What is known. The holdup is a natural gas pipeline, not a shortage of chips or capital. Project Jupiter’s on-site power is meant to come from Bloom Energy fuel cells fed by a roughly 17-mile “Green Chile” pipeline extension that Transwestern Pipeline, an Energy Transfer subsidiary, is building. New Mexico’s State Land Office has twice — in March and again in July 2026 — denied the pipeline a right-of-way across state trust land, and Energy Transfer’s own FERC filings now show the in-service date slipping from around September 2026 to February 1, 2027, according to El Paso Matters and corroborating trade coverage. A separate state air-quality permit for the fuel cells has also not been issued; a public hearing was delayed by litigation before a court cleared the process to resume. Financing details reported around the deal: a roughly $18 billion construction loan from a consortium of about 20 banks, against a total planned investment for the full multi-phase development that Bloomberg and other outlets put at up to $165 billion. Doña Ana County is set to receive $12 million a year for 30 years under the project’s tax agreement; a county commissioner told El Paso Matters that Oracle had not updated local officials on the delay. Both companies are playing down the significance: an Oracle spokesperson called force-majeure notices “commonplace in developments of this scale,” and Blue Owl said the notice “does not change the financial commitments to this multi-year project.” Oracle stock fell roughly 4% in premarket trading on the news, per Yahoo Finance.

What this means for capacity buyers. Project Jupiter is a hyperscaler-anchored build, not colocation capacity our catalog would carry — but the mechanism is directly relevant to anyone signing multi-year power or lease commitments in gas- and grid-constrained US markets right now. A force majeure clause tied specifically to “power commitments” is becoming a template response to permitting risk: landlords and lenders are being asked to absorb the schedule risk of state-level right-of-way and air-permit fights that neither party fully controls. That’s the same underwriting question we flagged in Texas’s permit-halt story — power and water access, not construction cost, is now the binding constraint on hyperscale timelines. For financing structures more broadly, see our AI data center financing guide; for how permitting delay compares across regions, our energy hub and colocation price index track where power is actually available versus merely announced.

What we don’t know. Whether Oracle will actually invoke the rent deferral or is simply preserving the option is unclear — neither company has said so. Reported figures on physical construction progress (some outlets cite roughly 26% campus-wide completion and around 10% for the fuel-cell microgrid) come from a single source we could not independently confirm, so we’re not treating them as established. It’s also unresolved whether the pending air-quality permit will clear before the pipeline’s new February 2027 target, and what happens to Doña Ana County’s tax revenue timeline if first-phase operations — originally targeted for late 2026 — slip further.

Frequently asked questions

What did Oracle do regarding Project Jupiter?

On September 24, 2026, Oracle sent developer Stack Infrastructure — owned by Blue Owl Capital — a force majeure notice tied to Project Jupiter, the 2.45-gigawatt data center campus it is building in Santa Teresa, New Mexico. The notice preserves Oracle's contractual right to defer rent payments for up to three years if the site's power infrastructure is not ready when the campus is due to open.

Why is Project Jupiter's power buildout delayed?

The campus depends on Bloom Energy fuel cells fed by a roughly 17-mile 'Green Chile' gas pipeline. New Mexico's State Land Office has twice denied Transwestern Pipeline, an Energy Transfer subsidiary, a right-of-way across state trust land, and the pipeline's FERC-filed in-service date has slipped from around September 2026 to February 2027. A separate state air-quality permit for the fuel cells is still pending.

Does the force majeure notice mean Project Jupiter is canceled?

No. Oracle said the notice does not by itself establish a delay or change delivery expectations, and Blue Owl said it does not change the project's financial commitments. Both companies describe force majeure notices as routine in developments of this scale; the practical effect is that Oracle keeps the option to defer rent if permitting keeps slipping.

Sources

Primary sources cited in this article. Every figure links to where it comes from.

  1. El Paso Matters: Oracle could defer Project Jupiter rent payments over power supply delays
  2. TechCrunch: Oracle sends force majeure notice on its New Mexico Stargate data center
  3. Yahoo Finance: Oracle Cites 'Force Majeure' to Shield Itself on Controversial Data Center
  4. Bloomberg: Oracle Cites 'Force Majeure' to Shield Itself on Controversial Data Center

Get Quotes

Tell us what you need — we match you with data centers in our catalog and return real quotes. Free for buyers.

We reply within one business day. No spam, no reselling your contacts.